← PortfolioCooper's HawkMid-Year Review · FY26
IT

Simphony POS Upgrade (PARENT)

Simphony POS Upgrade (PARENT)

Schedule: https://chwinery.sharepoint.com/:x:/r/sites/Project-NewPointofSaleSimphony/Shared%20Documents/General/Simphony%20Rollout/Locations_with_City_and_State.xlsx?d=wcd347620d6fd4061ab34d84457a2cbba&csf=1&web=1&e=YwEdWE

Stage
Base Business/Ongoing
Level
Level 1: Topline
Health
Complete
Latest Update · Nov 24, 2025

Complete

Department
IT
Strategic Pillar
5 ENABLE A STRONG FOUNDATION
Executive Sponsor
Dave H
Owner
IT Dependency
IT Roadmap
Yes
Fiscal Year / Quarter
Timing
Start Date
Target End
Budget
Status
Complete
Status Updates · 10
2y 2m running
CompleteNov 24, 2025
In Progress/On TrackMay 13, 2025

5.13.25: Group 4 Goes Live this week

In Progress/On TrackApr 18, 2025

Group 2 goes live on April 22 and 23

BehindOct 14, 2024

10.14: received no/go: Implementation was pushed to 2025 8.7.24: testing moved to ~8.27.24 (St. Charles)

BehindAug 7, 2024

8.7.24: testing moved to ~8.27.24 (St. Charles)

In Progress/On TrackJul 11, 2024

7.8.24: St Charles test was pushed back to July 23

In Progress/On TrackJul 8, 2024

7.8.24: St Charles test was pushed back to July 23 6.11.24 (LT): St Charles test begins July 9 with launch to follow; targeting completion by the end of October

In Progress/On TrackJun 16, 2024

6.11.24 (LT): St Charles test begins July 9 with launch to follow; targeting completion by the end of October

In Progress/On TrackMay 22, 2024

5.22.2024: Payroll and Accounting teams are engaged in configuration testing.

In Progress/On TrackMay 3, 2024

Prism · Cooper’s Hawk Strategy · Mid-Year Review FY26