← PortfolioCooper's HawkMid-Year Review · FY26
Learning & Development

WC Training: Sales and Coaching Modules (L&D) - COMPLETE

WC Training: Sales and Coaching Modules (L&D) - COMPLETE
Stage
Design (Build/Plan)
Level
Level 3: Dept Project
Health
Complete
Latest Update · Jan 9, 2026

1.8.26: Complete per Angela

Department
Learning & Development
Strategic Pillar
1 ACQUIRE NEW MEMBERS
Executive Sponsor
Chris C
Owner
Angela B
IT Dependency
IT Roadmap
Fiscal Year / Quarter
FY24 · Q2
Timing
Updated to FY24 delivery
Start Date
Target End
Budget
Status
Complete
Status Updates · 9
3y 1m running
CompleteJan 9, 2026

1.8.26: Complete per Angela

BehindOct 23, 2024

MANAGER TO JAN; TM COMPLETE - LAUNCH W/SERVER AND REMAINING ROLES 10.14.24: Moved to January 8.14.24: moved to September 8.1.24: moved to July 3.18.24: Updated module release see project for dates; target project completion for June 24 (coaching module)

BehindOct 14, 2024

10.14.24: Moved to January 8.14.24: moved to September 8.1.24: moved to July 3.18.24: Updated module release see project for dates; target project completion for June 24 (coaching module)

In Progress/On TrackAug 14, 2024

8.14.24: moved to September 8.1.24: moved to July 3.18.24: Updated module release see project for dates; target project completion for June 24 (coaching module)

In Progress/On TrackAug 1, 2024

8.1.24: moved to July 3.18.24: Updated module release see project for dates; target project completion for June 24 (coaching module)

In Progress/On TrackMar 20, 2024

3.18.24: Updated module release see project for dates; target project completion for June 24 (coaching module)

In Progress/On TrackDec 25, 2023

12.8.23 YE: Module 1 complete; Modules 2 and 3 in progress; Wine Club Culture and Coaching Performance to FY24 Q1

In Progress/On TrackDec 24, 2023

Oct 23: Video 1 launched to all locations; implementing enhancements; series to be completed in 2024

In Progress/On TrackMay 24, 2023
Project Action

Status Needed

Prism · Cooper’s Hawk Strategy · Mid-Year Review FY26