Operations Integration
Pack the House, Pop the Cork Challenge
Z_2026_CompletePack the House, Pop the Cork Challenge
Health
In Progress/On Track
Latest Update · Mar 5, 2026
Complete
Department
Operations Integration
Strategic Pillar
3 OPTIMIZE PERFORMANCE
Executive Sponsor
Tim M
Owner
Bryan W
IT Dependency
—
IT Roadmap
—
Fiscal Year / Quarter
FY25 · Q4
Timing
P9-P12
Start Date
Jun 15, 2025
Target End
Jul 31, 2025
Budget
—
Status
In Progress/On Track
Status Updates · 4
1y running
CompleteMar 5, 2026
In Progress/On TrackOct 10, 2025
Announcing the winners in November
In Progress/On TrackJun 18, 2025
Challenge is now open June 15-July 31
In Progress/On TrackMay 22, 2025
Prism · Cooper’s Hawk Strategy · Mid-Year Review FY26