Operations Integration
Clerestory Coffee Transition
Ops Integration ProjectsClerestory Coffee Transition
Health
—
Latest Update · Jun 22, 2026
6.22: Traunch 1- 34 locations transition completed. Traunch 2 - 34 locations transition between June 22 - July 23. 3rd/Final traunch - 17 locations July 28- Aug 13. Unopened coffee being picked up and/or shipped back for credit.
Department
Operations Integration
Strategic Pillar
—
Executive Sponsor
—
Owner
—
IT Dependency
—
IT Roadmap
—
Fiscal Year / Quarter
—
Timing
—
Start Date
—
Target End
—
Budget
—
Status
—
Status Updates · 1
8 days running
In Progress/On TrackJun 22, 2026
6.22: Traunch 1- 34 locations transition completed. Traunch 2 - 34 locations transition between June 22 - July 23. 3rd/Final traunch - 17 locations July 28- Aug 13. Unopened coffee being picked up and/or shipped back for credit.